Our projects

NATIONAL PAPER PRODUCER
DECEMBER 2019 - JUNE 2020
Medium and low voltage electrical system.
We install the electrical system from the medium voltage connection to transformers, low voltage panels, control panels, motor control centers, connection of loading and unloading pumps, ground system, lightning rod system, exterior lighting, HVAC and connection to instruments
Instrumentation system, automation and control.
Manufacture, installation and connection of control cabinets, PLC, installation of measuring instruments (pressure transmitters, level transmitters, densitometers, temperature transmitters, motorized valves)
Fiber optics, CCTV and structured cabling.
Installation of 4 6 km fiber optic infrastructure, fiber splicing through fusion of cores, assembly and connection of data center Implementation of photovoltaic panel system to energize wireless network system and CCTV on poles around railway tracks
NATIONAL PAPER PRODUCER
DECEMBER 2019 - JUNE 2020

Electric
• Winder Connection to a 2000 kVA transformer to a disconnector to feed motor control center for a paper winder Installation of CED 40 aluminum piping earth system
• Paper machine Installation and connection to new low voltage motor drives Renewal of piping and wiring for motor power supply
• Luminaires Development of engineering, installation and commissioning of LED lighting system inside the paper machine in extreme conditions of humidity and heat.
Automation, control and networks
• Winder Installation of ducting, wiring and connection for winder control system
• Paper machine Installation and connection to new low voltage motor drives Renewal of piping and wiring for motor control
• Optical fiber Laying of 500 meters of optical fiber for exterior in tray and connection by means of fusion of cores to communicate electrical network analyzer
AUTONEUM
FEBRUARY 2017 - JULY 2020

The supply, installation and commissioning of the electric power system including transformers and electric power plant, channeling, commissioning of 1 MDF and 4 IDF's with the suppression system, 600 network nodes, 54 IP cameras, 14 access controls, 4 vehicle controls, fire detection system, software and hardware to the payroll system in each of the plants
IMMSA GROUP
MEXICO
JUNE - JULY 2020

Maintenance of the control and instrumentation system of the dry, wet and electrolysis area during the scheduled shutdown of 2020
UPS system maintenance analysis of lead acid batteries, reporting and battery replacement Installation of 200 meters of fiber optics for connection to the contract office
Renovation of piping, wiring and connection to rotary valves

CITADELLA
OCTOBER
NOVEMBER 2018
Installation of piping, wiring and connection of 70 network nodes to main SITE Connection tests with DSX 8000 UTP cable certifier
Installation and connection of 20 card readers for access control Henywell

SCHOTT
GEMTRON SLP
Fiber optic connection of 6 IDFs, channeling and structured cabling for network nodes, supply, installation and commissioning of the CCTV system in the cities of San Luis Potosí, Monterrey and Veracruz.

BMW
SAN LUIS POTOSI
APRIL 2018
Supply and implementation of 2 data centers in their entirety, channeling and structured cabling for 1,000 network nodes.
Network cabling tests with DSX 5000 certifier.

SCHOTT
GEMTRON SLP
Fiber optic connection of 6 IDFs, channeling and structured cabling for network nodes, supply, installation and commissioning of the CCTV system in the cities of San Luis Potosí, Monterrey and Veracruz.